| EnergyView |
Weekly Brief · No. 3
Monday, 25 May 2026
|
The spark gap detailed.
Three numbers framed the week. Wind Energy Ireland confirmed zero onshore wind farms received planning permission in Q1 2026, with 15 projects waiting more than a year and six over two. Eurostat states at 40.42 c/kWh in H2 2025, Irish households now pay the highest electricity prices in the EU. And the Climate Change Advisory Council's wholesale gap between windy and fossil days is €85/MWh.
The structural answer everyone gave to the bill question — build more renewables, displace margin-setting gas — has been the right one for a decade.
| 01 | Stat of the week |
Onshore wind farms received planning permission in Ireland in Q1 2026 — with 15 projects waiting over a year in the queue and six waiting over two.
| 02 | News roundup |
9 items |
Sarah Carey: "playing with fire" on energy security — and the counter-argument arrived within 24 hours
Sarah Carey's column placed two LNG options head to head: New Fortress Energy's Ballylongford proposal (NFE has commissioned four LNG terminals in 36 months) against the state-led Cahiracon option, which has no commissioning timeline (estimated 2031). Her frame — Ireland has effectively zero days of strategic gas storage against Denmark's 181 and Greece's 37. Dan O'Brien's LinkedIn piece — argued the exposure on gas security is unforgivable.
In practice: the security-of-energy-supply is critical, and time is of the essence.
Ireland's electricity is Europe's most expensive — and the bill breakdown is now public
Eurostat confirmed Ireland H2 2025 at 40.42 c/kWh, ~40% above the EU average of 28.96 c/kWh — roughly €480/yr above the median European customer. The CSO's domestic energy index rose 42% YoY (+32.6% in April alone, fuel oil and gas oil leading). UCC's Paul Deane gave RTÉ the cleanest decomposition: roughly one-third generation, one-fifth network, one-quarter balancing and capacity, 10% taxes and renewable schemes, 10% supplier. CRU's interim review found no evidence of excessive supplier profits; the government has ruled out a windfall tax.
In practice: there is no demand-side lever in the system that answers a 40.42 c/kWh number. The only material moves are supply-side: more grid, more wind on the system, more interconnection, more storage. Which leads to the next two items.
The 2026 Climate Action Plan is five months late — and the underspend is the story
The Public Accounts Committee on 21 May is where the CAP delay stopped being a scheduling issue and became a delivery one. DECC Secretary General Oonagh Buckley told the committee CAP26 will arrive "in the coming weeks." Committee member Grace Boland (FG) called the slippage "intolerable." Of the €523.8m Climate Action Fund, €261m sits unspent. The €190m windfall levy revenue is mostly unspent. The EPA is projecting Ireland will hit a 23% emissions reduction by 2030 — against a binding 51% legal target.
In practice: the gap between binding target and projected delivery is now 28 percentage points. EPA updated projections are due within the next fortnight.
Wind hit 38% in April, but Q1 planning approvals were zero
EirGrid's April figures: wind 38% of generation, solar 6%, all-renewable 48%, first 1 GW solar peak recorded. System non-synchronous penetration ran near the 75% operating limit. Against that, Wind Energy Ireland's Q1 audit found zero onshore wind farms received planning permission, with 15 projects waiting over a year and six over two. The Oireachtas Joint Committee on Climate, Environment and Energy concluded on 20 May that the 5 GW offshore by 2030 target is "extremely unlikely" to be met. RWE's newly-proposed 13-turbine Mayo project — taller than the Dublin Spire, 110kV connection — joins the same queue.
In practice: with zero of the Phase 1 ORESS projects through planning, it is more than 'extremely unlikely' that the offshore target will be met at this stage.
SEAI signals fossil-heating phase-out — 2030 for industry, 2035 for homes
SEAI's Comprehensive Heating report, reinforced by CEO William Walsh's Journal interview, sets two markers: phase out fossil fuels from industrial heat by 2030 and from domestic heating by 2035. Walsh was careful to distinguish "phase-out" from "ban." Tallaght remains Ireland's only operating district heating scheme.
In practice: the heating phase-out cannot land on current policy. A 2035 domestic deadline implies an electrification or biomethane pull-through the present scheme stack doesn't deliver.
EirGrid: data centres must show 80% renewables matching — and AIRAA closes Wednesday
The CRU and EirGrid data centre connection process (CER/2025/236) requires new connections to demonstrate at least 80% renewable energy matching, with autoproducer status required for Tier A applicants. Fossil-islanded data centres are now "not in line" with policy. Data centre demand is projected at 9.4 → 14.6 TWh from 2025–2034 — share of national electricity demand rising from 22% to 31%. Separately, EirGrid's Adequacy in Ireland Reserve Adequacy Assessment (AIRAA) for 2027–2036 — methodology consultation — closes 16:00 on Wednesday 27 May at consult.eirgrid.ie.
In practice: the 80% renewables matching rule is the binding constraint on hyperscaler expansion. If they can't procure compliant PPAs at scale, future demand growth flattens and moves abroad.
Stream BioEnergy: €80m Cork plant plans to connects to GNI grid — Ireland's largest biomethane
Stream BioEnergy's Little Island, Cork facility signed contracts last week to connect to the Gas Networks Ireland grid. 80 GWh/yr from 2027 onwards, capital cost €80m, anaerobic digestion technology, enough biomethane to heat roughly 6,000 homes. Bia Energy's Dublin plant separately took "best biomethane development" at the All-Island Bioeconomy Summit.
In practice: more of these scale of plants are required to get as close as possible to the 5.7 TWh target. GNI confirmed only 11% of the target is contracted for grid connection.
Perigus Energy plans €600m Irish renewables build-out over 18 months
Perigus Energy — Cork-headquartered post the CIP €1.44bn Ørsted Ireland acquisition — confirmed a €600m investment programme over the next 18 months. Operational base today is 373 MW (wind), with 178 MW under construction. Two solar farms in execution: 55 MW at Ballinrea, Cork (planning secured for co-located BESS) and a second site in Carlow. CEO Kieran White's framing is to build Cork as the European platform.
IEA Global EV Outlook 2026: 30% global share, Europe +30% YoY in Q1
IEA's Global EV Outlook 2026 this week: 30% of global new car sales projected electric in 2026, Europe Q1 +30% YoY. The headline data point — roughly 70% of China-manufactured BEVs were already cheaper than equivalent ICE vehicles before incentives in 2025. Forty countries now have BEV market shares above 10%.
In practice: the cost-parity argument has crossed the line in the world's largest auto market.
| 03 | Open consultations |
3 worth answering |
| 27 May · Wed |
2 days left
EirGrid · AIRAA 2027–2036 methodologyAdequacy framework for the next decade. Closes 16:00 Wednesday. consult.eirgrid.ie
|
| Open Rolling |
SEAI · National Energy RD&D Programme€20m call open, includes new offshore Renewable Energy RDD+ pathway. seai.ie
|
| EoI Open |
DCEE · District Heating Pre-Construction FundExpressions of interest open. Tallaght-style schemes the implicit benchmark. gov.ie / dcee
|
| 04 | Job postings |
10 new · 8 open |
| 05 | Conferences & webinars |
| 25 May · Mon |
SEAI · National Energy RD&D webinarWalks through the 2026 €20m funding call. Online · today
|
| 26 May · Tue–Wed |
Wind Energy Ireland · Offshore Wind ConferenceTheme: moving the 20 GW by 2040 ambition into delivery. Clayton Hotel Burlington Road, Dublin · 26–27 May
|
| 17 Jun · Wed–Thu |
Energy Ireland 202630th anniversary of the flagship all-island conference. CRU Chair Aoife MacEvilly, SEAI CEO William Walsh, Bord na Móna's John Reilly and ESB's Paul Lennon in the line-up. Croke Park, Dublin · 17–18 Jun
|
| 18 Jun · Thu |
Solar Ireland 2026 — Energising LifeOverlaps day two of Energy Ireland — pick your panel. RDS, Dublin
|
| 24 Jun · Wed |
Biomethane Day Ireland 2026Two years on from the launch of Ireland's National Biomethane Strategy. Radisson Blu Royal Hotel, Dublin 8
|
| 30 Jun · Tue |
Energy Storage Ireland Annual ConferenceHogan Suite, Croke Park, Dublin
|
| 21 Oct · Wed–Thu |
Renewable Energy Expo Ireland 2026Joint conference between Wind Energy Ireland, Solar Energy Ireland and Energy Storage Ireland. Dublin · 21–22 Oct
|
| 22 Oct · Thu |
Convergence 2026 — Digital Infrastructure IrelandDII flagship. Data centres plus energy policy plus the EU Presidency framing. Croke Park, Dublin
|
| 18 Nov · Wed–Thu |
H2 Summit 2026 — Hydrogen IrelandCo-hosted with the Clean Hydrogen Partnership; anchored to Ireland's EU Presidency. Fota Island Resort, Cork · 18–19 Nov
|
Minister Dooley used his keynote to underline the role of the bioeconomy in Irish energy security — the first explicit ministerial framing of biomethane as a security-of-supply asset rather than only a decarbonisation one. Gas Networks Ireland used the same platform to confirm a material milestone: 11% of the 2030 biomethane target — roughly 627 GWh of the 5.7 TWh ambition — is now contracted for grid connection. Three years out from the deadline, that's the first hard delivery number GNI has put on the table.
