EnergyView
Weekly Brief · No. 3
Monday, 25 May 2026
This week

The spark gap detailed.

Three numbers framed the week. Wind Energy Ireland confirmed zero onshore wind farms received planning permission in Q1 2026, with 15 projects waiting more than a year and six over two. Eurostat states at 40.42 c/kWh in H2 2025, Irish households now pay the highest electricity prices in the EU. And the Climate Change Advisory Council's wholesale gap between windy and fossil days is €85/MWh.

The structural answer everyone gave to the bill question — build more renewables, displace margin-setting gas — has been the right one for a decade.

— Philip Connolly, EnergyView
01

Stat of the week

Q1 2026 wind planning
Zero

Onshore wind farms received planning permission in Ireland in Q1 2026 — with 15 projects waiting over a year in the queue and six waiting over two.

Source · Wind Energy Ireland Q1 2026 planning audit
02

News roundup

9 items
Energy security

Sarah Carey: "playing with fire" on energy security — and the counter-argument arrived within 24 hours

Sarah Carey's column placed two LNG options head to head: New Fortress Energy's Ballylongford proposal (NFE has commissioned four LNG terminals in 36 months) against the state-led Cahiracon option, which has no commissioning timeline (estimated 2031). Her frame — Ireland has effectively zero days of strategic gas storage against Denmark's 181 and Greece's 37. Dan O'Brien's LinkedIn piece — argued the exposure on gas security is unforgivable.

In practice: the security-of-energy-supply is critical, and time is of the essence.

Prices · Eurostat

Ireland's electricity is Europe's most expensive — and the bill breakdown is now public

Eurostat confirmed Ireland H2 2025 at 40.42 c/kWh, ~40% above the EU average of 28.96 c/kWh — roughly €480/yr above the median European customer. The CSO's domestic energy index rose 42% YoY (+32.6% in April alone, fuel oil and gas oil leading). UCC's Paul Deane gave RTÉ the cleanest decomposition: roughly one-third generation, one-fifth network, one-quarter balancing and capacity, 10% taxes and renewable schemes, 10% supplier. CRU's interim review found no evidence of excessive supplier profits; the government has ruled out a windfall tax.

In practice: there is no demand-side lever in the system that answers a 40.42 c/kWh number. The only material moves are supply-side: more grid, more wind on the system, more interconnection, more storage. Which leads to the next two items.

Policy · Climate Action Plan

The 2026 Climate Action Plan is five months late — and the underspend is the story

The Public Accounts Committee on 21 May is where the CAP delay stopped being a scheduling issue and became a delivery one. DECC Secretary General Oonagh Buckley told the committee CAP26 will arrive "in the coming weeks." Committee member Grace Boland (FG) called the slippage "intolerable." Of the €523.8m Climate Action Fund, €261m sits unspent. The €190m windfall levy revenue is mostly unspent. The EPA is projecting Ireland will hit a 23% emissions reduction by 2030 — against a binding 51% legal target.

In practice: the gap between binding target and projected delivery is now 28 percentage points. EPA updated projections are due within the next fortnight.

Renewables · Wind

Wind hit 38% in April, but Q1 planning approvals were zero

EirGrid's April figures: wind 38% of generation, solar 6%, all-renewable 48%, first 1 GW solar peak recorded. System non-synchronous penetration ran near the 75% operating limit. Against that, Wind Energy Ireland's Q1 audit found zero onshore wind farms received planning permission, with 15 projects waiting over a year and six over two. The Oireachtas Joint Committee on Climate, Environment and Energy concluded on 20 May that the 5 GW offshore by 2030 target is "extremely unlikely" to be met. RWE's newly-proposed 13-turbine Mayo project — taller than the Dublin Spire, 110kV connection — joins the same queue.

In practice: with zero of the Phase 1 ORESS projects through planning, it is more than 'extremely unlikely' that the offshore target will be met at this stage.

Heat · SEAI

SEAI signals fossil-heating phase-out — 2030 for industry, 2035 for homes

SEAI's Comprehensive Heating report, reinforced by CEO William Walsh's Journal interview, sets two markers: phase out fossil fuels from industrial heat by 2030 and from domestic heating by 2035. Walsh was careful to distinguish "phase-out" from "ban." Tallaght remains Ireland's only operating district heating scheme.

In practice: the heating phase-out cannot land on current policy. A 2035 domestic deadline implies an electrification or biomethane pull-through the present scheme stack doesn't deliver.

Grid · Data centres

EirGrid: data centres must show 80% renewables matching — and AIRAA closes Wednesday

The CRU and EirGrid data centre connection process (CER/2025/236) requires new connections to demonstrate at least 80% renewable energy matching, with autoproducer status required for Tier A applicants. Fossil-islanded data centres are now "not in line" with policy. Data centre demand is projected at 9.4 → 14.6 TWh from 2025–2034 — share of national electricity demand rising from 22% to 31%. Separately, EirGrid's Adequacy in Ireland Reserve Adequacy Assessment (AIRAA) for 2027–2036 — methodology consultation — closes 16:00 on Wednesday 27 May at consult.eirgrid.ie.

In practice: the 80% renewables matching rule is the binding constraint on hyperscaler expansion. If they can't procure compliant PPAs at scale, future demand growth flattens and moves abroad.

Biomethane

Stream BioEnergy: €80m Cork plant plans to connects to GNI grid — Ireland's largest biomethane

Stream BioEnergy's Little Island, Cork facility signed contracts last week to connect to the Gas Networks Ireland grid. 80 GWh/yr from 2027 onwards, capital cost €80m, anaerobic digestion technology, enough biomethane to heat roughly 6,000 homes. Bia Energy's Dublin plant separately took "best biomethane development" at the All-Island Bioeconomy Summit.

In practice: more of these scale of plants are required to get as close as possible to the 5.7 TWh target. GNI confirmed only 11% of the target is contracted for grid connection.

Investment

Perigus Energy plans €600m Irish renewables build-out over 18 months

Perigus Energy — Cork-headquartered post the CIP €1.44bn Ørsted Ireland acquisition — confirmed a €600m investment programme over the next 18 months. Operational base today is 373 MW (wind), with 178 MW under construction. Two solar farms in execution: 55 MW at Ballinrea, Cork (planning secured for co-located BESS) and a second site in Carlow. CEO Kieran White's framing is to build Cork as the European platform.

Transport · EV

IEA Global EV Outlook 2026: 30% global share, Europe +30% YoY in Q1

IEA's Global EV Outlook 2026 this week: 30% of global new car sales projected electric in 2026, Europe Q1 +30% YoY. The headline data point — roughly 70% of China-manufactured BEVs were already cheaper than equivalent ICE vehicles before incentives in 2025. Forty countries now have BEV market shares above 10%.

In practice: the cost-parity argument has crossed the line in the world's largest auto market.

03

Open consultations

3 worth answering
27 May · Wed
2 days left

EirGrid · AIRAA 2027–2036 methodology

Adequacy framework for the next decade. Closes 16:00 Wednesday.

consult.eirgrid.ie
Open Rolling

SEAI · National Energy RD&D Programme

€20m call open, includes new offshore Renewable Energy RDD+ pathway.

seai.ie
EoI Open

DCEE · District Heating Pre-Construction Fund

Expressions of interest open. Tallaght-style schemes the implicit benchmark.

gov.ie / dcee
04

Job postings

10 new · 8 open
New this week
EirGrid · Dublin — Senior Lead Analyst, Capacity Funding & Delivery
EirGrid · DublinStakeholder Engagement Analyst
SSE Renewables · DublinInvestment & Commercial Manager
Statkraft · Cork — Senior Grid Engineer
Ibec · Dublin — Head of EU and International Policy
Elgin Energy · Dublin — Head of Portfolio
SLR Consulting · Dublin — Process Engineer (Anaerobic Digestion)
Morgan McKinley · DublinInvestment Analyst, Energy & Infrastructure
AWS · Dublin — Senior Global Strategy Engineer
CTS Group · Greater Dublin — Data Centre Sustainability Lead
Still open from Brief 2
EirGrid — MD Offshore Closes 12 noon Fri 29 May
ESB — Senior Consenting Manager
EirGrid — Policy Governance Specialist
AWS — Director, EMEA Energy & Water
SSE — Head of Origination & Transactions
AWS — Power Solutions Manager
Bord na Móna — Offtake Partnership Manager
AIB — Associate Director, Portfolio Climate & Infrastructure Capital
Closed since Brief 2 · EAI CEO (22 May)
05

Conferences & webinars

This week — urgent
25 May · Mon

SEAI · National Energy RD&D webinar

Walks through the 2026 €20m funding call.

Online · today
26 May · Tue–Wed

Wind Energy Ireland · Offshore Wind Conference

Theme: moving the 20 GW by 2040 ambition into delivery.

Clayton Hotel Burlington Road, Dublin · 26–27 May
Coming up
17 Jun · Wed–Thu

Energy Ireland 2026

30th anniversary of the flagship all-island conference. CRU Chair Aoife MacEvilly, SEAI CEO William Walsh, Bord na Móna's John Reilly and ESB's Paul Lennon in the line-up.

Croke Park, Dublin · 17–18 Jun
18 Jun · Thu

Solar Ireland 2026 — Energising Life

Overlaps day two of Energy Ireland — pick your panel.

RDS, Dublin
24 Jun · Wed

Biomethane Day Ireland 2026

Two years on from the launch of Ireland's National Biomethane Strategy.

Radisson Blu Royal Hotel, Dublin 8
30 Jun · Tue

Energy Storage Ireland Annual Conference

Hogan Suite, Croke Park, Dublin
Save the dates · autumn
21 Oct · Wed–Thu

Renewable Energy Expo Ireland 2026

Joint conference between Wind Energy Ireland, Solar Energy Ireland and Energy Storage Ireland.

Dublin · 21–22 Oct
22 Oct · Thu

Convergence 2026 — Digital Infrastructure Ireland

DII flagship. Data centres plus energy policy plus the EU Presidency framing.

Croke Park, Dublin
18 Nov · Wed–Thu

H2 Summit 2026 — Hydrogen Ireland

Co-hosted with the Clean Hydrogen Partnership; anchored to Ireland's EU Presidency.

Fota Island Resort, Cork · 18–19 Nov
Post-conference debrief · All-Island Bioeconomy Summit 2026

Minister Dooley used his keynote to underline the role of the bioeconomy in Irish energy security — the first explicit ministerial framing of biomethane as a security-of-supply asset rather than only a decarbonisation one. Gas Networks Ireland used the same platform to confirm a material milestone: 11% of the 2030 biomethane target — roughly 627 GWh of the 5.7 TWh ambition — is now contracted for grid connection. Three years out from the deadline, that's the first hard delivery number GNI has put on the table.

"The EirGrid data centre connection framework is the single most consequential demand-side document set published in Ireland this decade. It turns hyperscaler growth into a force for renewables build — and its effects will compound across the rest of the 2020s and 30s."
Philip Connolly Editor · EnergyView

Keep Reading