| Energy●View | Weekly Briefing · No. 015 Monday, 17 August 2026 |
Huntstown connects, and solar has its week.
Ireland’s first direct biomethane connection went live at Huntstown on 12 August. One plant, up to 120 GWh a year, against a 2030 target of 5.7 TWh. The number to hold onto is six, the producers Gas Networks Ireland already has connection agreements with behind it.
Solar had the week of its life and then lost it. Grid-scale output hit an all-time 1,258 MW on Tuesday, then fell to 8 MW at the height of Wednesday’s eclipse before climbing back. Two consultations close today.
| 01 | Stat of the week |
Ireland’s highest ever grid-scale solar output, just before 1pm on Tuesday 11 August. Solar met roughly a third of national electricity use at that moment.
| 02 | Energy news | Top story + 6 |
Bia Energy connects the first plant directly to the gas network
Gas Networks Ireland connected Bia Energy’s €90m anaerobic digestion facility at Huntstown, Co Dublin, to the national gas network on 12 August, the first direct biomethane injection in the State. At full capacity the plant is expected to deliver up to 120 GWh of biomethane a year.
Gas Networks Ireland built a network extension and a new entry facility for the connection, and holds agreements with six further producers. Bia Energy, part of the Sretaw group, received almost €3.9m under the National Biomethane Strategy Capital Grant Scheme, and says the site will displace 3,000 tonnes of chemical fertiliser a year through digestate.
120 GWh is 2.1% of the 5.7 TWh biomethane target for 2030. Bia Energy is the first of seven producers holding connection agreements with Gas Networks Ireland, and the €19m issued in July under the 2024 capital grant scheme went to those same seven projects.
Watch the interval between Huntstown’s connection agreement and its first injection. It is the only Irish data point on how long that sequence runs, and the projects behind it will be planned against it. The next markers are the expression of interest round at the end of Q3 and registry issuance from January 2027.
Expression of interest process opens at end of Q3 for the next grant round
The next round of capital grants for biomethane plants will begin with an expression of interest process expected at the end of Q3 2026. Government began issuing €19m in July to the seven projects successful under the 2024 Biomethane Capital Grant Scheme, Bia Energy among them.
9.4% of July’s fuel mix came from grid-scale solar
EirGrid provisional data published 11 August put grid-scale solar at 9.4% of the July fuel mix, a monthly record, up from 8.2% in June and 5.7% in July 2025. Renewables overall reached 32.3%, against 32% in July 2025, as wind fell from 24.1% to 22.4% and generated 614 GWh. Gas supplied 43% and interconnection 24%, on system demand of 2,744 GWh.
Grid-scale solar then fell from 532 MW at 6.15pm on 12 August to 202 MW by 6.45pm and 8 MW at the height of the eclipse thirty minutes later, recovering to 83 MW by 7.45pm. EirGrid says the power system can now operate with up to 75% of electricity from variable renewables at any one time, with work under way to raise that to 95%.
CRU sets financial penalties at up to 10% of turnover
The Commission for Regulation of Utilities published its Financial Penalty Framework on 11 August, setting out how it will calculate penalties where regulated energy entities engage in improper conduct. Under the Electricity Regulation Act 1999 the CRU may impose penalties of up to 10% of a regulated entity’s turnover, subject to High Court confirmation.
The framework covers electricity and gas suppliers, network operators and interconnector operators, and combines a pre-determined calculation with discretion on the facts of each case. Timely remediation and compensation are treated as mitigating factors. The National Energy Affordability Taskforce Action Plan is due to government in September.
SSE secures consent for the Mullafarry battery project
Mayo County Council granted planning consent on 13 August for SSE’s revised plans at its proposed Mullafarry Battery Energy Storage System in north Mayo.
Separately, Grid System Services has applied to Roscommon County Council for a 44-block energy storage system at Ballaghaderreen, with a decision expected this week and more than 300 objections lodged.
48 projects and 2,668 MW await planning decisions
Wind Energy Ireland said on 11 August that 48 projects representing 2,668 MW of capacity are awaiting planning decisions. Five wind projects were approved in the second quarter of 2026, the highest quarterly total since the first quarter of 2025.
Heart Aerospace flies an 11,340 kg aircraft on batteries alone
Heart Aerospace’s X1 demonstrator completed its first flight on 12 August at Plattsburgh International Airport in New York, 27 minutes at up to 335 m on battery power alone. Takeoff weight was about 11,340 kg across a 32.3 m wingspan, making it the largest battery-electric aircraft flown to date. The propulsion system delivered more than 1 MW, and the company put the electricity cost of the flight at about five dollars.
X1 is a full-scale demonstrator for the ES-30, a 30-seat hybrid-electric regional aircraft with a stated 200 km all-electric range and entry into service targeted for 2031. EnergyView mapped that range from Dublin Airport. The 200 km radius covers almost the whole island. A 300 km battery upgrade adds Belfast, Derry and the western seaboard but leaves every London airport outside the battery-only band, at 464 km and up. Full workings and the radius map in this week’s carousel.
| ● | H&MV Engineering, the Limerick high-voltage firm serving data centres, battery storage and networks, was valued at €1.4bn in a new investment deal. RTÉ |
| ● | A six-month flexibility trial launched this week offers EV drivers up to €78 for charging at home at system-friendly times. TK operator. Business Plus |
| ● | 16,770 solar PV grants were paid by the Sustainable Energy Authority of Ireland in the first six months of 2026, worth up to €1,800 each. Irish Examiner |
| ● | 26% of new private cars licensed from January to July were electric, against 17% a year earlier, confirming the SIMI picture on a licensing basis. Central Statistics Office |
| ● | The Environmental Protection Agency published its quarterly greenhouse gas emissions indicator for Quarter 1 2026. TK headline figure. EPA |
| 03 | Open consultations | 2 close today |
| 17Aug · Mon | Closes today DCEE · Climate Action Plan update, climate priorities Priorities and measures for the second carbon budget period. Draft plan expected later this year. Consultation · Closes 17:30 |
| 17Aug · Mon | Closes today DCEE · Draft Bioeconomy Strategy 2026–2030 Feedstock, circularity and the policy frame around anaerobic digestion. Relevant to AD developers. Consultation · Closes 17:00 |
| 27Aug · Thu | 10 days left DCEE and EirGrid · RESS 6 qualification window Hard gate, not a consultation. Two pots, wind and solar separately. Eight hours or more of storage duration earns the maximum 0.075 storage score. RESS 6 · Qualification |
| 28Aug · Fri | 11 days left Department of Transport · Draft National Ports Policy Investment in Ports of National Significance, with additional east coast capacity flagged as needed post-2040. Relevant to offshore wind port readiness. TK link · Closing date confirmed 28 August |
| 04 | Job postings | 2 open |
Gas Networks Ireland is carrying two roles in functions the biomethane build-out will lean on. An EirGrid role closing 28 August is TK pending confirmation of the title.
| Gas Networks Ireland Cork or Dublin | Senior Network Planning Engineer Network Planning, reporting to the Network Planning Manager. Apply · Ref GNI137 · No closing date published |
| Gas Networks Ireland Cork or Dublin | Customer Relationship Manager, Regulatory Affairs Regulatory Affairs, Shipper Services team. Apply · Ref GNI141 · No closing date published |
| 05 | Conferences & webinars | Next 13 weeks |
| 26Aug · Wed | ESB and Hydrogen Ireland · Hydrogen in a Net Zero Power System Hydrogen specialists and industry professionals on hydrogen’s role in a cleaner, more secure and resilient energy system. 11:00–13:00 · Online · Register |
| 28Sep · Mon | Informal meeting of EU energy ministers Dublin, under the Irish Presidency. Runs 28 and 29 September. Two days · Dublin · Presidency listing |
| 21Oct · Wed | Renewable Energy Expo Ireland 2026 RDS Dublin. Wind Energy Ireland, Solar Ireland and Energy Storage Ireland together for the first time. Two days · Dublin · renewableenergyexpo.ie |
| 29Oct · Thu | Transport, Telecommunications and Energy Council (Energy) Formal Council under the Irish Presidency. Networks package and ETS revision are the stated priorities. All day · Council of the EU · Formal |
| 09Nov · Mon | COP31 Antalya, Türkiye, 9 to 20 November. Ireland leads EU negotiations as Presidency holder. Two weeks · Antalya · UNFCCC |
| 06 | Podcast corner |
Mansoor, President and chief executive of the Electric Power Research Institute, argues over how much electricity AI will actually need, whether hyperscaler capital expenditure is justified, and how greater flexibility could let data centres connect faster without overwhelming the grid. The passages on public acceptance and on the role of nuclear are the ones that travel.
Ireland is unlikely to become a location for AI model training in the near term, given electricity prices. Around 100 data centres already operate here, and Ireland remains an attractive location for new cloud capacity.
